Timelapse video – construction 5 MW geothermal wellhead plant

This video shows a timelapse of the construction of a 5 MW flash-condensing geothermal wellhead power plant. The plant was built for the client Kenya Electricity Generating Company (KenGen). Construction on the site took 30 weeks, from the civil works, laying the foundations to the connection to the grid and […]

Read More

GEG progresses construction of first 2 plants in Kenya

Green Energy Group reports progress on the construction of the first geothermal wellhead plant as part of the larger contract with KenGen. OLK-02 is now taking shape with cooling towers, gen-sets and control room having been set up. “Everything is progressing according to plan and GEG expects to commission the […]